BWS Kapiolani Boulevard Project

A Board of Water Supply (BWS) contractor is working to replace approximately 3,800 feet of water main and appurtenances along Kapiolani Boulevard from McCully Street to Date Street.  The BWS understands that Kapiolani Boulevard is a highly-traveled thoroughfare and created this web page to provide the community with project and traffic updates.  Additionally, customers can call 748-5310 to get voice recordings with updated information.

This important project will improve fire protection, reduce the likelihood of main breaks, and enhance water service to residents and businesses in the area.

CLICK HERE FOR PROJECT MAP

PROJECT OVERVIEW

  • The project involves the replacement of approximately 2,800 feet 12-inch waterline and approximately 1,000 feet of 8-inch water main and related equipment on Kapiolani Boulevard from McCully Street to Date Street.
  • The project start date is March 31, 2014.
  • Contractor: RMY Construction, Inc.
  • For questions or concerns contact the project construction manager, ESH Inc. at 799-8744, BWS Construction Section at 748-5730 or BWS Communications Office at 748-5041.

PROJECT AND TRAFFIC UPDATES AS OF OCTOBER 17, 2014.

Please be advised of traffic modifications and lane closures on Kapiolani Boulevard from McCully Street to Date Street.  Motorists traveling through the construction area are asked to observe all traffic signs, traffic signals, expect delays, drive with caution, allow for additional travel time, and use alternate routes where possible.

  • Working area: Kapiolani Boulevard and McCully Street intersection.
  • Type of work: Installation of 12-inch water main.
  • Lane closures:

    Monday, October 20, and Tuesday, October 21, from 8:30 a.m. to 3:30 p.m.
    • One Ewa-bound lane of Kapiolani Boulevard between McCully Street and Wiliwili Street will be closed;
    • The left turn lane onto Kapiolani Boulevard from the makai-bound direction of McCully Street will be closed; and
    • One mauka-bound lane of McCully Street will be closed at the Kapiolani Boulevard intersection.

    Wednesday, October 22, to Friday, October 24, from 8:30 a.m. to 3:30 p.m.
    • Two makai-bound lanes of McCully Street between Kapiolani Boulevard and Lime Street will be closed; and
    • The mauka-bound lanes of McCully Street between Kapiolani Boulevard and Lime Street will be contra-flowed.

    Additional lane closures may be implemented each day and shift depending on the work area and project needs.
  • Working hours: Working hours: Monday to Friday from 8:30 a.m. to 3:30 p.m.

*There will be no work from November 26-30, in observance of the Thanksgiving holiday.

Note: This website provides current project information as it becomes available. Please note that there may be times where lane closures could change without notice.

 

Monday, October 20, and Tuesday, October 21, from 8:30 a.m. to 3:30 p.m.
•    One Ewa-bound lane of Kapiolani Boulevard between McCully Street and Wiliwili Street will be closed;
•    The left turn lane onto Kapiolani Boulevard from the makai-bound direction of McCully Street will be closed; and
•    One mauka-bound lane of McCully Street between Kapiolani Boulevard and Lime Street will be closed.
Wednesday, October 22, to Friday, October 24, from 8:30 a.m. to 3:30 p.m.
•    Two makai-bound lanes of McCully Street between Kapiolani Boulevard and Lime Street will be closed; and
•    The mauka-bound lanes of McCully Street between Kapiolani Boulevard and Lime Street will be contra-flowed.